641M .         Pre‑operational monitoring program

        (1)         The mine operator of a relevant mine must ensure that a mining operation does not commence at the mine unless —

            (a)         before mining operations commence at the mine, the mine operator submits to the regulator a program for the mining operation (a pre‑operational monitoring program ) to monitor radiation levels and dose levels at the mine; and

            (b)         the regulator approves the program under subregulation (2); and

            (c)         the mine operator provides the results of the program to the regulator.

        Penalty for this subregulation:

            (a)         for an individual, a fine of $4 200;

            (b)         for a body corporate, a fine of $21 000.

        (2)         The regulator may approve, by written notice, a pre‑operational monitoring program for a mining operation at a mine if the program is appropriate.

        Note for this subregulation:

                Not approving a pre‑operational monitoring program for a mining operation under this subregulation is a reviewable decision (see regulation 676).

        (3)         In making a decision under subregulation (2), the regulator may have regard to a guideline that is —

            (a)         approved by the regulator for the purposes of this subregulation; and

            (b)         published on the regulator’s website.