The mine operator of a
mine is taken to have complied with regulation 675UK(2) in relation to a
high risk mining activity listed in column 1 of the Table and occurring
before, on and after commencement day if, before commencement day, the action
under the MSIA that is listed opposite the high risk mining activity was taken
in relation to the activity.
Table
Column 1 High risk mining activity |
Column 2 Action under MSIA |
---|---|
Schedule 23 item 1 |
Written notification was provided under the MSIR regulation 12.3(1) in
relation to the mine shaft |
Schedule 23 item 2 in relation to installing a winding system |
Written notification was provided under the MSIR regulation 11.3(1) in
relation to the winding system |
Schedule 23 item 2 in relation to making major changes to an already
installed winding system |
Written notification was provided under the MSIR regulation 11.6(1) in
relation to the modification of the winding system |
Schedule 23 item 3 |
The winding system was approved under the MSIR regulation 11.4 and tested
under the MSIR regulation 11.5 |
Schedule 23 item 4 |
The method was approved by the senior inspector under the MSIR
regulation 10.21(1) |
Schedule 23 item 7 |
Written advice was provided to the district inspector under the MSIR
regulation 10.19(2)(a) in relation to the construction |
Schedule 23 item 8 |
Written notification of the fuel storage or refuelling facility was provided
under the MSIR regulation 10.58(1) |
Schedule 23 item 10 |
Application for approval for the use of the dredge was sought under the MSIR
regulation 14.4(5) |
Schedule 23 item 11 |
Approval of the commencement of mining operations was sought under the MSIA
section 42 in relation to the tailing storage facility |
Schedule 23 item 12(a) |
Notification of the use of the explosives in reactive ground was given under
the MSIR regulation 8.55(2) |
Schedule 23 item 12(b) |
Notification of the use of the explosives in hot ground was given under the
MSIR regulation 8.54(3) |
Schedule 23 item 13 |
Approval of the commencement of mining operations was sought under the MSIA
section 42 in relation to the mobile plant or production drilling plant |
Schedule 23 item 14 |
Provision of complete details of the high voltage installation occurred under
the MSIR regulation 5.18(2)(a) |