(1) This regulation
applies to a mine where a site senior executive must be appointed.
Note for this subregulation:
See
regulation 675ZH in relation to when an offence is committed if a site
senior executive is not appointed at a mine.
(2) Before mining
operations commence at the mine, the person who is the prospective mine
operator of the mine must give the regulator notice of the appointment of a
person to be the site senior executive of the mine, including any other
information or document relating to the appointed person that the regulator
requires.
(3) The person who
becomes the mine operator of a mine when mining operations commence at the
mine commits an offence if the mining operations commence without the person
having complied with subregulation (2).
Penalty for this subregulation:
(a) for
an individual, a fine of $4 200;
(b) for
a body corporate, a fine of $21 000.
(4) If there is a
change in the person who is the site senior executive of a mine, the mine
operator of the mine must, no later than 7 days after the date of the
change, give the regulator notice of the change, including any other
information or document relating to the new site senior executive that the
regulator requires.
Penalty for this subregulation:
(a) for
an individual, a fine of $4 200;
(b) for
a body corporate, a fine of $21 000.
(5) If a person gives
notice to the regulator under subregulation (2) or (4), the
regulator may require the person to provide the regulator with any
clarification of the contents of the notice, or with any supplementary
information or document.
(6) A person who is
required to provide the regulator with a clarification of the contents of the
notice, or with any supplementary information or document, under
subregulation (5) must comply with the requirement as soon as
practicable.
Penalty for this subregulation:
(a) for
an individual, a fine of $4 200;
(b) for
a body corporate, a fine of $21 000.
(7) If there is a
change in any information or document provided to the regulator under
subregulation (2), (4) or (6), the mine operator of the mine
must provide the regulator with the updated information or document no later
than 7 days after the date of the change.
Penalty for this subregulation:
(a) for
an individual, a fine of $4 200;
(b) for
a body corporate, a fine of $21 000.
(8) Any notice,
clarification, information or document that is required to be given or
provided to the regulator under this regulation must be given or provided
using, and include information required by, an approved form and in a manner