(1A) In this
regulation —
WHS management plan means the initial plan and all
revised versions of the plan.
(1) Subject to
subregulation (2), the principal contractor for a construction project
must ensure that a copy of the WHS management plan for the project is kept
until the project to which it relates is completed.
Penalty for this subregulation:
(a) for
an individual, a fine of $1 450;
(b) for
a body corporate, a fine of $7 000.
(2) If a notifiable
incident occurs in connection with the construction project to which the
statement relates, the person must keep the WHS management plan for at least
2 years after the incident occurs.
Penalty for this subregulation:
(a) for
an individual, a fine of $1 450;
(b) for
a body corporate, a fine of $7 000.
(3) The person must
ensure that, for the period for which the WHS management plan must be kept
under this regulation, a copy is readily accessible to any person who is to
carry out construction work in connection with the construction project.
Penalty for this subregulation:
(a) for
an individual, a fine of $4 200;
(b) for
a body corporate, a fine of $21 000.
(4) The person must
ensure that for the period for which the WHS management plan must be kept
under this regulation, a copy is available for inspection under the Act.
Penalty for this subregulation:
(a) for
an individual, a fine of $1 450;
(b) for
a body corporate, a fine of $7 000.
(5) [not used]