The principal
contractor at a construction site must ensure that at all times when
tilt‑up work is being done at the site there is kept at the
site —
(a) if a
concrete panel that is, or is to be, involved in the work was manufactured at
a place other than the construction site, the copy of the notification to the
regulator given under regulation 306B(4) to the principal contractor in
respect of the panel; and
(b) if a
concrete panel that is, or is to be, involved in the work was manufactured at
the construction site, a copy of the notification under
regulation 306B(2) given to the regulator in respect of the panel; and
(c) a
copy of any exemption under Part 11.2 relating to the work; and
(d) a
copy of the shop drawings of each concrete panel that is, or is to be,
involved in the work; and
(e) a
current plan setting out details of the proposed execution of the work; and
(f) a
copy of any written or diagrammatic advice, from a qualified practising
engineer, received by the principal contractor, that sets out the manner in
which an aspect of the work should be executed; and
(g) in
relation to each concrete panel that is, or is to be, involved in the work, a
copy of the inspection report for that panel referred to in
regulation 306C(1)(d) or (2)(d), as is relevant to the case.
Penalty:
(a) for
an individual, a fine of $7 000;
(b) for
a body corporate, a fine of $35 000.