(1) After protection work is completed, the owner of relevant premises must serve a complete set of drawings and specifications, showing the protection work carried out, on (a) each adjoining owner; and(b) if building work or demolition work is to be performed at the relevant premises, the relevant building surveyor; and(c) if plumbing work is to be performed at the relevant premises, the relevant permit authority.Penalty: In the case of (a) a natural person, a fine not exceeding 100 penalty units; or(b) a body corporate, a fine not exceeding 500 penalty units.(2) A building surveyor who receives a complete set of drawings and specifications under this section must provide a copy of those drawings and specifications to the relevant permit authority.