BUILDING ACT 2016 (NO. 25 OF 2016) - SECT 315

Evidence of compliant demolition work
(1)  Unless evidence is provided to the contrary, demolition work is taken to comply with this Act if it complies with the relevant performance requirements of the National Construction Code.
(2)  Unless evidence is provided to the contrary, demolition work is taken to comply with the relevant performance requirements of the National Construction Code if –
(a) in relation to permit demolition work –
(i) a demolition permit is issued in respect of the demolition work; and
(ii) a certificate of completion is issued in respect of the demolition work; and
(b) in relation to notifiable demolition work, a certificate of completion is issued in respect of the demolition work.