Cancellation of temporary occupancy permit
(1) A building surveyor, or permit authority, may cancel a temporary
occupancy permit in respect of a building or temporary structure if satisfied
that (a) a person is using, or is intending to use, the building
or temporary structure for a use (i) other than that stated in the
temporary occupancy permit; or
(ii) to which the building or structure may not
be used; or
(b) a person occupying the building or temporary structure fails
to comply, or is intending not to comply, with any condition of the temporary
occupancy permit; or
(c) a building order or emergency order made in respect
of the building, or temporary structure, has not been complied with; or
(d)
building work has been, or is to be, carried out on the building or temporary
structure other than in accordance with this Act; or
(e) the building or
temporary structure is unsafe, unhealthy, or unfit for occupation by, or a
danger to, persons.
(2) In addition to any penalty imposed under section 233 , a
temporary occupancy permit in respect of a building or temporary structure is
automatically cancelled if a person is found guilty under that section in
respect of the temporary occupancy permit.