BUILDING ACT 2016 (NO. 25 OF 2016) - SECT 196

Duration of demolition permit
(1)  A demolition permit expires on the first of the following:
(a) if the permit specifies a period within which the permit demolition work is to be commenced and no work has commenced within that period, on the expiry of that period;
(b) if no permit demolition work has been commenced under the permit and the permit does not specify a period within which the work is to be commenced, on the first anniversary of the permit application being granted under section 193 ;
(c) if the permit does not specify a period for which it is in effect and the period for which it is in effect is not extended under section 197 , on the second anniversary of the permit application being granted under section 193 ;
(d) if the permit specifies a period for which it is in effect and the period for which it is in effect is not extended under section 197 , on the expiry of the period specified in the permit;
(e) if the period for which the permit is in effect is extended under section 197 , on the expiry of the period so extended;
(f) on the issuing of a certificate of completion (permit demolition work) in respect of the permit demolition work to be performed under the permit.
(2)  A demolition permit is only valid while the permit is in effect.