BUILDING ACT 2016 (NO. 25 OF 2016) - SECT 127

Certificate of completion (notifiable demolition work)
(1)  A person may apply to the relevant building surveyor for a certificate of completion (notifiable demolition work) in respect of completed notifiable demolition work.
(2)  An application under subsection (1)  –
(a) is to be in an approved form; and
(b) must include a copy of the standard of work certificate (notifiable demolition work) issued in respect of the notifiable demolition work.
(3)  On receipt of an application under subsection (1) , a building surveyor may only issue a certificate of completion (notifiable demolition work) if satisfied that –
(a) the completed notifiable demolition work has been performed in accordance with this Act; and
(b) the applicable building administration fee has been paid in respect of the work.
(4)  Within 7 business days after issuing a certificate of completion (notifiable demolition work), the building surveyor who issued the certificate must forward a copy of the certificate to the relevant permit authority.