Certificate of completion (notifiable demolition work)
(1) A person may apply to the relevant building surveyor for a
certificate of completion (notifiable demolition work) in respect of completed
notifiable demolition work.
(2) An application under subsection (1) (a) is to be
in an approved form; and
(b) must include a copy of the standard of work
certificate (notifiable demolition work) issued in respect of the notifiable
demolition work.
(3) On receipt of an application under subsection (1) , a building
surveyor may only issue a certificate of completion (notifiable demolition
work) if satisfied that (a) the completed notifiable demolition
work has been performed in accordance with this Act; and
(b) the applicable
building administration fee has been paid in respect of the work.
(4) Within 7 business days after issuing a certificate of completion
(notifiable demolition work), the building surveyor who issued the certificate
must forward a copy of the certificate to the relevant permit authority.