(1)  Within the prescribed period after notifiable plumbing work is completed, the responsible person for the work must –
(a) provide the relevant permit authority with –
(i) a standard of work certificate (notifiable plumbing work) for the work; and
(ii) a copy of any as-constructed plans of the work that have not previously been provided to the permit authority; and
(b) provide a copy of the standard of work certificate (notifiable plumbing work) to the owner of the premises where the work was performed.
(2)  A standard of work certificate (notifiable plumbing work) is to be in an approved form.
(3)  For the purposes of this section, notifiable plumbing work is only completed after –
(a) the work has been inspected as required under section 111 ; and
(b) the person performing the inspection is satisfied that the work complies with this Act and the National Construction Code.