(1) Within the prescribed period after notifiable building work is completed, the responsible person for the work must (a) provide the relevant building surveyor with (i) a standard of work certificate (notifiable building work) for the work; and(ii) a copy of any as-constructed plans for the work that have not previously been provided to the building surveyor; and(b) provide a copy of the standard of work certificate (notifiable building work) to the owner of the premises where the work was performed.(2) A standard of work certificate (notifiable building work) is to be in an approved form.(3) For the purposes of this section, notifiable building work is only completed after (a) the work has been inspected as required under section 100 ; and(b) the person performing the inspection is satisfied that the work complies with this Act and the National Construction Code.